COMPLETE LIST OF UPCOMING PROJECTS:
School
Project
Estimated Cost
Cleveland Elementary
Roof replacement
$2,621,500
Cooper Elementary
New 125 Ton Chiller
$133,750
East Clayton Elementary
Replace chillers and cooling tower (HVAC)
$449,400
Four Oaks Elementary
Replace Roof(Butterfly Building)
$531,790
Pine Level Elementary
Replace Front End & Controllers (HVAC)
$294,250
Selma Elementary
Replace Roof (Buildings 4, 5, 6, 8)
$1,863,699
Clayton Middle
Roof replacement
$5,243,000
Selma Middle
Roof Replacement
$4,010,895

Replace Chiller (HVAC)
$321,000
Smithfield Middle
Replace Roof
$749,000
Clayton High
Demo & Replace Football Bleachers
$205,065
North Johnston High
Replace Controllers, Hydronic Pipe Insulation & Piping, Gym Equip. (HVAC)
$920,200
Smithfield-Selma High
Replace Controllers, Hydronic Pipe Insulation, Coiling Issues (HVAC)
$361,125

Replace Roof
$5,890,885
South Johnston High
Replace Roof (Main Building)
$5,838,455
Meadow School
Replace controllers (HVAC)
$240,750
Princeton M/High
Replace controls (HVAC)
$374,500




TOTAL
$30,049,264